Day 1 Thursday 30 April, The day setting up commences with all the wiring to be installed for all the layouts & traders, the halls to be marked out, tables to be distributed, Crowd barriers to be placed. It is a very busy day which commences at 0800 in the morning.
Hall one & hall two before the transformation commences.
Cabinets for the ‘N’ gauge stand & Competition stand start to be unloaded.
Ladders to hand to start installing the electrics
Halls one & two start to take shape, all the electrics, tables & crowd barriers are in and its 5pm. Some traders have arrived along with a few of layouts
Two of the attending layouts being assembled.
Some of the Crew assembling the office, although Richard is having problems getting his words out. got tongue tied..